Freeze the scope facts
Record property type, suite or strata context, structural change, fixture moves, plumbing, electrical, ventilation and exterior penetrations.
Approval resolver
Route project facts through current City residential and plumbing sources, electrical authority, structural, suite and strata questions.
Decision file
Record property type, suite or strata context, structural change, fixture moves, plumbing, electrical, ventilation and exterior penetrations.
Use current City information to ask whether the actual construction scope needs building review; do not rely on a generic renovation answer.
Map fixtures and rough-in changes, who obtains the plumbing permit, inspections and closeout documents.
Route outlets, lighting, heating, fans, controls and panel work through current Technical Safety BC or applicable processes.
Record wall or floor changes, fire and acoustic assemblies, common property, alteration approval and building access.
Log authority, date, project facts, answer, application or inspection, owner and open dependency.
Describe property type, suite or strata context, wall and floor changes, fixture moves, plumbing, electrical, ventilation and exterior penetrations consistently to each authority. Save dated responses with the supplied facts.
Map City building and plumbing questions, Technical Safety BC electrical work and any structural or strata review into separate rows. Assign application, inspection, correction and closeout responsibility for each accepted scope item.
Add approval identifiers and required inspection points to the project schedule. Require trades to use the accepted drawing revision, document concealed work and file final records before the bathroom is treated as complete.
Keep separate rows for Surrey building and plumbing routes, electrical authority steps, structural review and suite or strata decisions. For each, record the actual project facts supplied, source, date, responsible party, application, inspection, condition and closeout document. Tie approvals to the current plan revision and schedule required hold points before concealment. Recheck changed fixture locations, walls, penetrations or electrical scope. The register coordinates processes without treating a general City webpage, earlier verbal answer or another unit’s renovation as permission for this bathroom.
Primary references
Links checked in the approved research packet on August 26, 2026. Applicability still depends on the property and proposed scope.